Thursday, 25 July 2019

EXAMPLE 4.9.1. PEBBLES AND WASHOUT FINISHES

A 2m x 10m wall is roughly plastered and requires stone pebble washout finish. Estimate the materials.



Concrete Volume method:

Determine the wall area:

          

Assuming the desired thickness of the pebbles is 12mm,


             

From Concrete Volume Table:





MIXTUREPROPORTION40kg50kgSANDGRAVEL


CEMENT
CEMENT








AA
1:1.5:3
12.0
9.5
0.50
1.0
A
1:2:4
9.0
7.0
0.50
1.0
B
1:2.5:5
7.5
6.0
0.50
1.0
C
1:3:6
6.0
5.0
0.50
1.0








Factor method:









Back to 4.0. Estimating Tiles