Saturday, 20 July 2019

2.7. ESTIMATING CONCRETE SLABS BY THE AREA METHOD

With the aid of a table, the area method for estimating concrete can be used easier than volume or weight method. In this topic, slab does not necessarily mean the horizontal pavement but also vertical slabs like concrete walls.

Procedure:

  1. Determine the area of the slab.
  2. Using the table, identify the proportions of cement, sand, and gravel, after figuring the required concrete class and the thickness of the slab.


SLAB THKABCABCSANDGRAVEL
(40KG)(40KG)(40KG)(50KG)(50KG)(50KG)
cmbagsbagsbagsbagsbagsbagscu.m.cu.m.
5.0 0.450 0.375 0.300 0.350 0.300 0.350 0.0250 0.050
7.5 0.675 0.563 0.450 0.525 0.450 0.375 0.0375 0.075
10.0 0.900 0.750 0.600 0.700 0.600 0.500 0.0500 0.100
12.5 1.125 0.938 0.750 0.875 0.750 0.625 0.0630 0.125
15.0 1.350 1.125 0.900 1.050 0.900 0.750 0.0750 0.150
17.5 1.575 1.313 1.050 1.225 1.050 0.875 0.0880 0.175
20.0 1.800 1.500 1.200 1.400 1.200 1.000 0.1000 0.200
22.5 2.030 1.688 1.350 1.575 1.350 1.125 0.1125 0.225
25.0 2.250 1.875 1.500 1.750 1.500 1.250 0.1250 0.250
27.5 2.475 2.063 1.650 1.925 1.650 1.375 0.1380 0.275
30.0 2.700 2.250 1.800 2.100 1.800 1.500 0.1500 0.300




No comments: