A drainage construction is to be estimated to run on a 850m highway. Using class A, determine the cement, sand, and gravel needed if the pipe is 1m diameter.
Volume method:
With Class A:
Using Per Pipe Piece Table:
Back to 2.0 Estimating Concrete
2.7. Estimating Concrete Slabs by the Area Method
2.8. Estimating Concrete Columns by Linear Meter Method
2.9. Estimating Circular Columns
2.10. Estimating Concrete Pipes
No comments:
Post a Comment