EXAMPLE 2.10.3. ESTIMATING DRAINAGE CONSTRUCTION

A drainage construction is to be estimated to run on a 850m highway. Using class A, determine the cement, sand, and gravel needed if the pipe is 1m diameter.

Volume method:

          

With Class A:


           

           

          


Using Per Pipe Piece Table:

                      