1.0 CONSTRUCTION PRE-PLANNING

Before the construction of a certain project will commensurate, planning within the owner, designer and the contractor should be accomplished properly. The Project Manager is the entity who shall make sure that the project will be complete at the target date according to the quality expected. 

ASSESSMENT COVERAGE: NETWORK DIAGRAM AND IDENTIFICATION OF CRITICAL PATH


Wednesday, 5 February 2020

TAPING: DETERMINING AREA OF RECTILINEAR FIELD BY TAPE

The tape can also be used to measure angles and not just for distances. By performing the chord bisection method or the 3:4:5 method, angles can be determined.

Click here for pdf file on Field work

Sunday, 2 February 2020

2.0. INTRODUCTORY CONCEPTS OF PERT/CPM

With the complexity of having too many activities to complete a project, construction should have a PERT/CPM schedule for management to determine the availability of:

  • Labor
  • Materials
  • Cost
  • Time
Although scheduling can be done with Gantt Chart, there are still advantages of learning the basics of CPM.